Trending Topics – How a Cold March Day in Texas Exposed the Value of Flexibility, and What Markets Can Learn

A version of this article was originally published on April 24th, 2017 on Greentech Media.

By Eric Gimon

As the sun rose over Dallas on Monday, March 3rd, 2014, the temperature read 15°F. Across the state, Texans turned on their heaters at full blast as they prepared to head to work for the day. Meanwhile, at the operations center for Texas’ electricity system (Electric Reliability Council of Texas, or “ERCOT”), operators saw the price of electricity skyrocket: around 8 AM prices jumped to nearly $5000/MWh, more than 100 times the average price of electricity.

Though the unusually cold weather caused demand for electricity to increase well above historical levels, the market behaved as intended. Many power plant owners, who know that their capacity is typically not needed this time of year, had their plants offline for maintenance. Thus when a period of unusually high demand came along on March 3rd, and with relatively low supply, prices skyrocketed, demonstrating the fundamentals of supply and demand. Power plants that were available and able to turn on quickly – to be flexible – to meet the spike in demand were rewarded handsomely.

As the renewables transition continues apace, flexibility will become increasingly important. Policy-makers and investors will need to watch carefully how flexibility is paid for.


In a market design like the “energy only” market in Texas, price spikes are a normal and important part of the market’s functioning, properly reflecting the marginal cost of electricity at that specific time, assuming no market manipulation. They provide an indication of how much and what types of resources are needed.

When spikes happen at predictable times of system needs, like during the summer when high temperatures cause increased electricity demand for air conditioning, they provide a good investment signal for peak capacity. When they happen at unusual times like the March 3, 2014 event, they provide a crucial signal to both buyers and sellers in the wholesale market of a need for investment in more flexible resources that can make themselves available at times of stress, on either the generation side or on the demand side. Too many of these unusual “bellwether” events indicate a system short on flexibility, while too few signal a system that is oversupplied (or lucky).

Bellwether events

Because flexible resources allow grid operators to respond rapidly to large changes in supply or demand, the frequency and magnitude of bellwether events are indicative of the need for flexible resources. In 2014, a handful of these bellwether events provided about 20-25 percent of net revenues for one typical Texas combined-cycle plant, indicating that the market was willing to pay for flexible resources. But in 2015 and 2016, due to plant owners keeping their units online more often, the addition of new capacity, and milder weather, the same plant garnered hardly any net revenue from bellwether events, indicating that there was no longer any need for extra flexibility.

How is this relevant for policy-makers and investors? Because of the variable nature of renewable resources, which create greater swings in the supply mix over smaller time-scales, the number of bellwether events is likely to grow as more and more cheap wind and solar power enters the Texas market. With over 5,000 MW of solar projected to come online by 2021, Texas is likely to need more flexibility in the coming years.

As the market continues rewarding flexibility, the resource mix could change substantially, which would impact the market in other ways. For example, if more combined cycle gas plants come online, they can help address flexibility needs, but will compete with baseload generators much of the year, which could increase downward pressure on already low wholesale prices. Alternatively, new flexible generation resources, like fast-start simple-cycle gas turbines, natural gas-fired diesel engines, demand-side resources, or storage could also respond to bellwether events. They would not change the market during ordinary times because they will be deployed only in times of stress when they capture the most value. To achieve the most cost-effective solution, market operators must allow resources of all types and sizes to participate by ensuring as transparent, accessible, stable, and technology-neutral an energy market as possible.

To a great extent, the investment signal for flexible resources is well handled in “energy-only” markets like ERCOT. As the need for flexible resources grows, there will be an increasing number of bellwether events; resource developers are likely to respond by building new resources that can capture this value on the spot market and through bilateral contracts with utilities. However, not all markets are structured to reward flexibility in the same way as in energy-only markets.

Different kinds of markets

Most electricity markets in the U.S. have additional payments or requirements outside of the energy market aimed at ensuring reliability. These payments, often administered through a “forward capacity market,” are meant to improve the economics of investing in new power plants and maintaining existing ones to ensure there is sufficient capacity available during times of peak demand. But forward capacity markets have traditionally focused on ensuring there is enough capacity to meet the peak level of demand over the course of the year, without giving much thought to the relative flexibility of that capacity.

The March 3rd cold spell in Texas provides a valuable lesson on why looking only at annual peak demand, rather than the need for flexible resources throughout the course of the year, can be problematic. When using capacity markets to ensure long-term reliability, it is not exactly clear what capacity to pay for when procuring “reliability” ahead of time. Reliability means different things at different times, and under different resource mixes. If forward capacity markets strictly reward market participants for meeting system peak demand, as they have traditionally done, market operators may not necessarily be rewarding the type of flexible capacity needed in bellwether events.

In theory, energy-only markets like ERCOT in Texas and markets with forward capacity markets should aim to be equally efficient at providing an economical and reliable grid. They should roughly compensate system resources for investing in new flexibility at a similar value. However, forward capacity markets tend to divert revenues from the energy market, and in so doing dilute the strength of the energy market signal to value resource flexibility. These out-of-market mechanisms have traditionally failed to consider the relative flexibility of capacity resources.

In energy-only markets like ERCOT, after new or upgraded system resources enter the market they capture the value of the reliability they provide when the system is stressed and prices spike, or by contracting forward with wholesale buyers to provide mutually beneficial risk management. If a resource cannot respond efficiently to short-term volatility, it will miss out on the associated opportunities and will be unable to offer wholesale buyers the risk-management services they need.

With a forward capacity market, the principle way to manage bellwether events is to supplement revenues by rewarding resources disproportionately for being available during prescribed periods ahead of time. If a resource fails to produce when called on it is usually penalized, either through foregone payments or directly through a penalty administered by the market operator. In both cases, a system resource that fails to make itself available during periods of system stress, like a bellwether event, is taking a big gamble by missing out on a significant amount of revenue, and in some cases a large fraction of its annual revenue. Resources that can respond quickly during such events avoid the costs incurred by less flexible resources that must operate unprofitably for hours or even days before and after the events to be sure they’re available when most needed.

If capacity markets expand their scope from anticipating peak supply needs to ensuring year-round reliability indiscriminately, they run the risk of significantly overpaying for reliability. Paying all types of resources to be available at all times, as opposed to paying just those resources that can more surgically be available in times of system stress, means buying a lot of extra reliability when it is unneeded. Furthermore, overly broad definitions of a capacity product may leave surgical flexibility providers unable to make a profit, even though they could provide a lot of reliability value. Think, for example, of a demand response provider being asked to be available every day of the year for up to eight hours, when the real need is to participate in a handful of bellwether events for three or four hours.

One fix involves tweaking the capacity market design to cover a broader definition of system needs, e.g. as in Hitting the Mark on Missing Money. Another involves creating a more iterative Staircase Capabilities Market design.

Learning across markets

In order to meet the flexibility challenge of shifting the future resource mix to cleaner, cheaper sources, markets with or without capacity markets must learn from each other. If an energy-only market sees a proliferation of very expensive bellwether events, such that net revenues from these much exceed capacity payments seen in other markets, their regulators and rate-payers should ask why more resources aren’t becoming available to meet the underlying need for investment in flexible supply- and demand-side resources. Conversely, if capacity markets are paying out relatively larger sums than those energy-only markets pay out through bellwether events, they should be questioning their framework for compensating resources to ensure reliability. In any case, to achieve least-cost reliability in a clean energy future, all markets should be inclusive towards all possible technologies – including demand-side options – that mitigate the impacts of bellwether events like that cold morning in Texas.